Construction project construction contract (power 1) Model text
reference text
No.:
-- ┌
│ this │
-- └
power construction project construction contract
project name
construction unit
construction unit
signing time
signing place
power construction project construction contract conditions
Chapter I meaning of words and contract documents
Article 1 meaning of words
power construction project construction contract The text is composed of the conditions of contract for the construction of electric power construction projects (hereinafter referred to as the conditions of contract) and the terms and conditions of the contract for the construction of electric power construction projects (hereinafter referred to as the terms and conditions of the agreement). Unless otherwise agreed in the terms and conditions of the agreement, its terms and expressions should have the meaning given by this article:
I The employer (hereinafter referred to as Party A): the party who has the qualification of contracting the project and the ability to pay the project price as agreed in the terms of the agreement
II. Party A's on-site representative (hereinafter referred to as Party A's representative): the representative designated by Party A in the terms of the agreement
III. contractor (hereinafter referred to as Party B): the party agreed in the terms of the agreement, who has the qualification of project contracting subject specified in the measures for the administration of power construction enterprise qualification and is accepted by the employer
IV. Party B's on-site representative (hereinafter referred to as Party B's representative): the representative designated by Party B in the terms of the agreement
v. social supervision: the supervision of the project by engineering supervision units or personnel entrusted by Party A and qualified in the measures for the administration of the qualification of electric power engineering construction supervision units
VI. chief supervision engineer: the chief supervisor appointed by the project supervision unit
VII although they have also developed various small panel control systems and design units: design units entrusted by Party A with the corresponding qualification levels specified in the measures for the administration of qualification of electric power engineering survey and design units
VIII. Project cost management department: relevant departments of the State Council, construction administrative departments at all levels or construction project cost management institutions authorized by the above departments
IX. engineering quality supervision departments: Ministry of electric power industry, electric power administration bureau, provincial (municipality directly under the central government, autonomous region) Electric Power Bureau or its electric power construction engineering quality supervision institutions established in accordance with the Interim Provisions on quality supervision of electric power capital construction projects
X. project: permanent project of power construction with specific contents as agreed in the terms of the agreement
Xi. Contract price: take the current quota, material budget price and corresponding charging standard as the guiding price, and determine it through bidding or negotiation between Party A and Party B to pay the total price of Party B's performance and completion of the project construction
XII. Economic expenditure: the contract price
issued during construction and paid in the form of increased budget after confirmation by Party A
XIII. Expenses: expenses directly paid by Party A beyond the contract price or expenses borne by Party B
XIV. Construction period: the contract period agreed by Party A and Party B in the terms of the agreement with reference to the duration quota of the power construction project
XV. Commencement date: the commencement date of the project agreed in the terms of the agreement
XVI. Completion date: the project completion date agreed in the terms of the agreement
XVII. Drawings: all drawings (including supporting instructions and relevant materials) provided by Party A or Party B and approved by Party A's representative for construction by Party B
XVIII. Construction site: the site for construction determined by the "construction organization design" or "construction plan" with the consent of Party A
XIX. Written form: various notices, appointments, commissions, certificates, visas, memoranda, minutes of meetings, letters, confirmed telegrams, telexes, etc. in writing, typing, copying and printing according to the contract
twenty Huaibei city also promotes demonstration and utilization in many ways, force majeure: explosion and fire caused by war, unrest, falling of flying objects in the air or other natural disasters that are not caused by Party A and Party B, as well as wind, rain, snow, earthquake and other natural disasters that cause damage to the project and performance of the contract above the level agreed in the terms of the agreement
XXI. Compensation: the costs of Party A to make up for the direct and indirect losses of the other party, including the actual costs of downtime, idling, rework, personnel and mechanical equipment relocation, overstock of materials and components, reshipment of labor costs, machinery costs, management fees and other actual costs, as well as the loss of benefits such as the interest accrued from the date these costs are payable
XXII. Quality defects: the project does not meet the quality requirements of the current relevant national or industrial technical standards, design documents and contracts
XXIII. Terms of the agreement: a written agreement signed by Party A and Party B according to law after negotiation in combination with the specific project
Article 2 contract documents and order of interpretation
first, contract documents should be able to interpret and explain each other. Unless otherwise agreed in the contract, its composition and interpretation order are as follows:
1. Terms of agreement
2. conditions of contract
3. Negotiation, change and other documents that clarify the rights and obligations of both parties
4. Notification of award, tender and bidding documents of the bidding contract project
5. Bill of quantities or project budget and drawings to determine the project cost
6. Standards and specifications. At the same time, various experimental data processing software, experimental auxiliary tools and other relevant technical materials and technical requirements can be customized according to the domestic and international standards provided by users
7. Other documents forming part of the contract
II. In case of ambiguities or inconsistencies in the contract documents, it shall be solved by both parties through negotiation without affecting the progress of the project (if social supervision is implemented, the chief supervision engineer can explain it first); If the two parties still cannot reach an agreement, it shall be solved according to the method agreed in Article 30
Article III language used in contract documents